EWL_Logo.gifEWL_Turbine.jpg

EWL Obermatt

Project Name: EWL Obermatt
Company: ABB Schweiz AG
Date: In progress, started in 2009
Place: Obermatt (CH)
Technology: ABB System 800xA - Industrial IT, with AC 800M & PLC Connect
Activities:
Software Engineering & Commissioning
Trouble shooting
Website: EWL
Project participants
Zoltan BabicsTrouble shooting
Patrick BoetschSoftware Engineering & Commissioning

Patrick was responsable for the migration of the existing control system, that was based on traditional relay technology from the 1960's, towards the ABB System 800xA - Industrial IT. He implemented the application software on the AC 800M controllers and the graphics for the operator interface, on hehalf of the turbine control.

Zoltan his expertise on the PLC Connect package was consulted, in order to solve some technical problems with the 800xA System.